Passleader MB6-884 PDF Exam Questions Are Best Preparation Materials To Pass Exam (11-20)

QUESTION 11
You create a project flow activity and select the option to register scrap. Where do you define the scrap factor that will be applied on backflushing?

A.    in the inventory and warehouse parameters
B.    in the production control parameters
C.    in the BOM lines
D.    in the product masters

Answer: A

QUESTION 12
You are setting up the following three process activities in a production flow in Microsoft Dynamics AX 2012: . The first process activity picks the bill of materials (BOM) components and outputs a semi-finished product. . The second process activity picks the semi-finished product from the first activity and outputs a different semi-finished product than the first activity. . The third process activity picks the semi-finished product from the second activity and outputs a finished product. How should you configure the first process activity?

A.    To update the on-hand receipt and not receive the semi-finished product
B.    To update the on-hand receipt and receive the semi-finished product.
C.    To receive the semi-finished product and not update the on-hand receipt.
D.    To not receive the semi-finished product and not update the on-hand receipt.

Answer: B

QUESTION 13
You are creating a sales order. You need to use the Capable to Promise (CTP) option as the Delivery date control setting. What must you do first? (Each correct answer presents part of the solution. Choose two.)

A.    Set the Automatic planning value on the Kanban rule to 1.
B.    set the sales lead time to 0 days.
C.    Set up a dynamic plan and assign it to the Master Planning parameters.
D.    Set the configuration key for Master Planning.

Answer: BC

QUESTION 14
When does the Capable to Promise (CTP) functionality allow the user to see the availability of products in Microsoft Dynamics AX 2012? (Each correct answer presents a complete solution. Choose two.)

A.     in a batch job after the sales order lines are entered.
B.    When a scheduled Kanban is generated.
C.    Automatically when an order is entered.
D.    After the View pegging tree requirement is selected on the sales order.

Answer: C

QUESTION 15
When filtering the supply schedule, which filter is required?

A.    Warehouse
B.    Site
C.    Plan
D.    Product dimensions

Answer: D


PassLeader[11]

http://www.passleader.com/mb6-884.html

QUESTION 16
You are creating a rule for an event Kanban. You need to ensure that Kanban cards automatically print when the first job of the Kanban flow is registered as In Progress. Which Automatic printing option should you use?

A.    Start
B.    Plan
C.    Receive
D.    Prepare

Answer: D

QUESTION 17
From where can you manually create an event Kanban for Kanban line events? (Each correct answer presents a complete solution. Choose two.)

A.    pegging tree
B.    sales order line
C.    Kanban board for process jobs form
D.    Kanban rules form

Answer: CD

QUESTION 18
Which form should you open from a sales order to determine the availability of Kanbans?

A.    Kanban calculation policies form
B.    Pegging tree form
C.    Kanban rules form
D.    Konbon board for process jobs form

Answer: C

QUESTION 19
When creating an event Kanban, which setting links the Kanban rule to the production flow version?
 
A.    Last plan activity
B.    Product selection
C.    First plan activity
D.     Replenishment strategy

Answer: B

QUESTION 20
When inventory transactions for completed quantities are processed as financially updated during the backflush costing calculation, which status is the receipt status updated to reflect?

A.    Ordered
B.    Sold
C.    Purchased
D.    Received

Answer: A


Passleader MB6-884 PDF Exam Questions Are Best Preparation Materials To Pass Exam

http://www.passleader.com/mb6-884.html